Three Corners Solar – Benton, ME
The Three Corners Project in Benton Maine is progressing well and on schedule. The concrete work for the foundations and pads has been completed by the skilled and hard working team. They have ensured the [...]
Mattawamkeag Bridge Replacement – Mattawamkeag, ME
Reed & Reed is in the final stages of the new Mattawamkeag Bridge on US Rt.2 in Mattawamkeag, Maine for the Maine Department of Transportation. The new bridge opened to traffic on September 15, 2022 [...]
Woolwich Station 46 Route 1 Bridge
The detour is now open and traffic is flowing smoothly. Demolition is underway on the existing bridge in preparation for construction of the new 4-span structure which will follow the same alignment as the existing [...]
West Virginia Wind Turbine Projects Completed at Pinnacle and Blackrock
The Reed & Reed-Bechtel Joint Venture team recently completed work on two major wind projects in the mountains of West Virginia. The Pinnacle Wind project included removing 23 existing MHI wind turbines, modifying the concrete [...]
RoxWind Project Resumes Work
After a winter shutdown, work has resumed on Reed & Reed’s RoxWind project in Oxford County, Maine. Last fall crews began sitework and completed foundations. This spring work has begun in earnest on the collector [...]
Black Rock Wind – West Virginia
NEW WIND FARM TO INCREASE WEST VIRGINIA’S WIND POWER BY NEARLY 15% Bechtel and Reed & Reed joint venture selected to deliver new Black Rock Wind Farm RESTON, Virginia, January 2021 — Clean, renewable energy [...]
York, Maine Open Road Tolling Project
The York toll Plaza looks much different than it did a year ago. In June we met the project schedule milestone of completing the Northbound and Southbound high-speed toll lanes so that the Turnpike’s vendor [...]
Barter’s Island Bridge Replacement
The replacement of the old swing span bridge is progressing quickly now as we near the completion stages of the job. The center swing span was recently floated into position and fitted with mechanical components [...]
VISIT our FB page for updates – We’re Hiring NOW!
Reed & Reed is looking for Wind Turbine Erectors for an exciting opportunity in Maine! Apply online at now.
Ossipee Bridge Project
The Ossipee Bridge project is well into its second construction season after a very successful first season. The $17 million project consists of replacing three red-list bridges and reconstructing 3.5 miles of roadway on busy [...]