News

York, Maine Open Road Tolling Project

The York toll Plaza looks much different than it did a year ago. In June we met the project schedule milestone of completing the Northbound and Southbound high-speed toll lanes so that the Turnpike’s vendor can start their 126-day commissioning phase. We have placed the two cornerstones of the project, the ORT slabs that will be the centerpieces of the new high-speed tolling lanes. We’ve also installed the cast-in-place median barrier, the spaceframes, miles of conduit and cabling, tolling devices, and panels needed for the high-speed toll lanes.
We’ve started work on the five toll islands, cash slabs, canopies, and tunnel stairs. Later this fall we will move traffic to the center lanes and finish the outside cash lanes of the project.
Subcontractors have help set over 7,500’ of precast barrier and placed over 14,000 tons of asphalt so far The Administration Building work was wrapped up in May even though the Turnpike isn’t going to take occupancy until near the end of the project.
We are working towards wrapping up the project in June 2021.

By |2020-09-16T15:31:48+00:00September 16th, 2020|

Barter’s Island Bridge Replacement

The replacement of the old swing span bridge is progressing quickly now as we near the completion stages of the job. The center swing span was recently floated into position and fitted with mechanical components and we’ve just placed the deck. The control house is filled and all of its’ control equipment will operate everything once the bridge is complete.
Due to the nature of this type of project, there are a lot of details that need to be precisely organized and tracked to ensure proper operation of the bridge. The mechanical components require installation within a fraction of an inch for proper operation. This includes installation of the center rotation bearing, balance wheels, live load rollers, end casters, end seats, end jacks, and end stops; all of which have been installed in the field under the span with hundreds of bolts, and countless shim plates to make sure they are all properly oriented to each other.
We expect to complete the project in the Fall of 2020.

By |2020-09-16T15:38:17+00:00September 16th, 2020|

Ossipee Bridge Project

The Ossipee Bridge project is well into its second construction season after a very successful first season.  The $17 million project consists of replacing three red-list bridges and reconstructing 3.5 miles of roadway on busy Route 16 in Ossipee, NH.

In our first season, Reed & Reed primarily focused on constructing and completing the bridge slide for the Bearcamp Relief Bridge, a 170’ two-span bridge over a bypass channel for the Bearcamp River. New substructures were built in the existing roadway and under the existing bridge while the entire new bridge superstructure was built 15 ft. away on temporary supports. Then during an 84-hour window in September, Reed & Reed demolished the existing bridge, slid the new bridge horizontally 50 ft. and lowered it onto its permanent bearings. We completed the work in 72 hours, 12 hours ahead of schedule.

Following completion of the Bearcamp Relief bridge, our team moved on to constructing the Lovell River bridge in a more conventional manner. We built a detour bridge and are constructing the new Lovell River Bridge on-line.  We also began substructure work at the Bearcamp River bridge, the largest of the three bridges to be replaced. This is also a slide-in bridge like the Relief bridge and is due to be completed in September.

Finally, our subcontractor AJ Coleman has completed a large portion of the Route 16 roadway rehabilitation on the project.  They will be completing most of their other earthwork this summer and will finish paving following the Bearcamp River bridge slide.

We hope to be substantially complete on the project later this year.

By |2020-04-07T18:16:46+00:00April 7th, 2020|

TEMPORARY SHUTDOWN

In view of the current and anticipated risks associated with the COVID-19 virus, we have decided that Friday April 10 Reed & Reed will discontinue construction operations for at least 2 weeks in order to provide for maximum protection of our employees during what is projected to be the peak level of infections.
All employees will receive full pay and benefits for the duration of the shutdown. No one will be laid off or furloughed.
These are extraordinary and unprecedented times that require extraordinary actions by all of us. As a company, Reed & Reed understands the worry and concerns you all have about COVID-19. We understand and share your concerns about the safety and well-being of your families. We also know that without you, our employee-owners, we cannot accomplish anything. We are taking this extraordinary action to shut-down all work because your health and safety is our number one priority. Period.
By |2020-04-07T15:07:03+00:00April 7th, 2020|

I-91 Bridge Replacement – Rockingham, VT

The new south bound bridge (Phase 2) of the $44 million I-91 Rockingham VT Bridge Replacement Project is underway.  The new north bound bridge (Phase 1) is now carrying NB & SB traffic of Vermont I-91 over the Williams River.

The new 880-foot-long bridges are 4-span structures, with spliced concrete beams and concrete bridge decks.  The bridge decks are 130 ft. above the Williams River.  This project is Reed & Reed’s first ever spliced concrete beam bridge.  The beam structure consists of five runs of 7 individual concrete beams that were installed on temporary support framework, aligned and held in position with thirty steel strong backs.  Cast in place concrete closures were placed between the ends of the beams and then three, 19 strand tendons running from abutment to abutment were installed and tensioned.  Crews will be grouting the tendon and working on the concrete deck and barrier for the south bound bridge.  Work is expected to complete this season.  Once the new SB bridge is open, the temporary crossovers will be removed and traffic restored fully in both directions.

By |2020-04-07T14:47:46+00:00April 6th, 2020|

Weaver Wind Project

After years of planning and permitting, work is finally underway at the Weaver site in Hancock County, Maine.  As Engineer-Procure-Construct (EPC) contractor, Reed & Reed’s scope includes installing 22 Vestas V126, 3.45MW turbines on 116.5-meter towers, all sitework, construction of a new Operations and Maintenance facility, overhead and underground electrical/fiber collection systems and 34.5/115kV electrical substation.

These towers are among the tallest in the Americas with the hub height at 382 feet and the blade tips reaching some 585 feet.  They will compliment similar towers at the nearby Hancock Wind project which Reed & Reed built in 2016 and the adjacent Bull Hill Wind Project, also built by Reed & Reed, in 2012.

The first turbine deliveries begin in February and will continue into the spring, weather and road conditions permitting.  Final completion and commercial operation for this $150 million project are scheduled for late 2020.

By |2019-12-16T13:07:27+00:00December 16th, 2019|

Reed & Reed installs Submarine Transmission Line in NY

Reed & Reed crews have completed installing two new submarine power cables under Seneca Lake in upstate New York.  The cables are each 16,000 feet long and lay on the lake bottom where water depths reach 600 feet.  Near shore where the water is shallow the cables were installed in trenches and backfilled.  Reed & Reed’s work also included installing new riser structures and switches on both the east and west sides of Seneca Lake where the new lines come ashore.  Fiber optic data and communications lines were also installed as part of the project scope.

Once the new cables were installed and energized Reed & Reed removed four existing cables that followed the same route but were installed in the 1940s.  The new cables are a significant upgrade to the local transmission grid and increase reliability as well as adding back-up capacity.

The project was years in the planning stages.  The new submarine cables were manufactured for Reed & Reed to exacting specifications by the Kerite Company, cabled together and armored in Florida, and delivered to the area by rail on a 150,000-pound cable reel that Reed & Reed loaded onto its barge for the trips across the lake.

Increasingly challenging fall weather in the Finger Lakes region forced the cable laying barge into safe harbor at times but the Reed & Reed crews found calm water work windows in which to install the new lines.  Hats off to the entire Reed & Reed project crew.

By |2019-12-04T21:19:10+00:00December 4th, 2019|

Antrim, NH Wind Project

Sometimes the pre-construction phase of a project can be longer that the actual construction phase.  Such is the case at the Antrim wind project where Reed & Reed has been in a support role for over 9 years. But happily, in April 2018 the project finally received the go ahead to build. We mobilized in July 2018 and our civil subcontractor Sargent Corporation started moving earth. We had a little over 3 miles of access roads to build, as well as 9 Turbine pads, O&M building subgrade fill, and a Substation yard. Reed & Reed’s substation crew built the collector substation yard while waiting for turbine deliveries to begin in May, 2019.  Foundations are complete and mud season is almost behind us.

Reed & Reed’s electrical team is building the underground and overhead collector systems and the project substation.

We will move one of our M-16000 top-out cranes to Antrim to erect the nine Siemens 2.3mw turbines on 80-meter towers.  The work is scheduled for a September 2019 final completion.

By |2019-04-19T18:18:44+00:00April 19th, 2019|