Darryl Coombs

About Darryl Coombs

This author has not yet filled in any details.
So far Darryl Coombs has created 14 blog entries.

Frank J. Wood Bridge Project

Work on the Frank J. Wood Bridge between Brunswick and Topsham, ME continues to advance with the bridge deck now completed. This major milestone sets the stage for the next phases of work, which include utility relocations and roadway tie-ins. Crews have already relocated water and communication lines to the new bridge, while efforts to shift electric and gas lines are ongoing. Additional relocations are planned on both the Brunswick and Topsham sides in preparation for the eventual traffic transition.

Pedestrian railings, architectural lighting, and other finishing details are being installed to ensure the bridge is both functional and visually appealing. Looking ahead, the project team will be racing against the calendar to open the new bridge to traffic by the end of the year. Once complete, the new bridge will provide smoother traffic flow, modern safety features, and improved pedestrian access for the community.

Reed &Reed crews will then shift focus to demolition of the existing 3-span truss bridge and its substructures. Once the old bridge has been removed work will begin on the final phase of hardscape improvements at each end of the project, which include seating areas, landscaping and riverine viewing panoramas.

By |2025-10-10T17:54:46+00:00October 10th, 2025|

Maine Maritime Academy Pier Project Update

Construction of the new Maine Maritime Academy Waterfront Facilities is well underway. The two-phase project will provide berthing for the Academy’s new training vessel as well as upgrades to other facilities along the waterfront.

Phase One includes a new pier supported by 243 steel pipe piles socketed 10 feet into bedrock. Precast and cast-in-place concrete pile caps will support precast deck panels and a cast-in-place concrete deck. In addition, Reed & Reed crews are building three new pile supported mooring dolphins, a precast concrete breakwater and new docking facilities for the Academy’s fleet of watercraft and training vessels.

With the Phase One concrete pier in place, crews will install all-new fender panels, bollards and various other enhancements plus utilities. Then it’s on to Phase Two of the project, which entails demolition of the existing timber pier and construction of a driven pile supported pier which will connect the newly built pier to land.

Resiliency is a key design element of the project. The pier incorporates upgraded materials and construction techniques to withstand tidal pressures, ice, and severe coastal storms. Environmental protection measures are also in place to minimize turbidity, protect marine habitats, and comply with regulatory standards during construction. When finished, the upgraded pier will be a robust and modern facility, providing a state-of-the-art training environment for the Academy’s fleet and programs for decades to come.

By |2025-10-10T17:47:55+00:00October 10th, 2025|

Twin Energy Wind Project Update

Twin Energy’s renewable wind project in western Maine has reached a significant milestone with the start of blasting operations on South Twin Mountain. This work marks the beginning of a critical stage in site preparation for the installation of three GE wind turbines, each designed to generate 6.1 MW of clean energy. In early September, controlled blasting began to clear bedrock and make way for turbine foundations and access roads across the rugged project site in Rumford and Roxbury.

The blasting is being conducted under strict safety protocols and environmental oversight. Real-time monitoring ensures that impacts to nearby ecosystems and residences are avoided. Weekly environmental inspections are being conducted to evaluate dust and vibration control, wildlife and habitat protection, and full compliance with environmental standards. These measures reflect the project’s commitment to advancing renewable energy in a responsible manner.

Once stable roadways are established Reed & Reed crews will build the massive concrete turbine foundations prior to delivery large of turbine components. Installation of underground drainage and electrical systems will be completed in time to support turbine erection in the early summer, 2026. Reed & Reed will mobilize its massive MLC 650 crane to the site to erect the turbines on their 117-meter towers.

With completion targeted for October 2026, the project is on track to provide clean, reliable power to thousands of homes across New England, furthering Twin Energy’s commitment to expand renewable energy capacity across the region.

By |2025-10-10T17:40:25+00:00October 10th, 2025|

Augusta Western Avenue Bridge Replacement

In Augusta, work on replacing the Western Avenue Bridge continues to move forward rapidly. This project addresses a critical transportation corridor and is designed to improve traffic flow, safety, and long-term durability. The existing structure, which had reached the end of its service life, is being replaced with prefabricated bridge units (PBUs) fabricated in the Reed & Reed casting yard. This Accelerated Bridge Construction (ABC) solution allows for a shortened construction phase and minimized interference with traffic.

Before demolition work could begin, Reed & Reed designed and built a three-lane temporary detour bridge carrying Western Avenue traffic over busy I-95. Once traffic is shifted onto the new bridge, crews will remove the temporary bridge and complete final paving, landscaping and clean-up prior to the June 2026 contract completion date.
The new Western Avenue Bridge will enhance safety and efficiency for motorists, cyclists, and pedestrians, while providing the region with a modern, low-maintenance structure capable of serving the community for decades.

By |2025-10-10T17:22:50+00:00October 10th, 2025|

Frank J. Wood Bridge Project

Frank J. Wood Bridge Project

The Frank J. Wood Bridge between the towns of Brunswick and Topsham made great progress this fall in preparation for steel erection this winter.

After the challenging floods of January 2024, the crew hit the water in August to knock out cofferdams at Piers 1 & 2.  Not the easiest of cofferdams to build as they were sitting directly on exposed ledge just below the dam, but the crew made quick work of them to make way for pier construction.   Meanwhile another crew was wrapping up construction of Abutment 1 and reconfiguring forms & liner to hit the two remaining piers full steam.

Currently the bridge substructure is complete, and steel erection is well underway with giant steel girders arriving each week from Pennsylvania.  The curved girders vary in length and weight, ranging up to 119 feet and 95,000 pounds.  With completion of steel erection wrapping up before spring, crews will begin building the bridge deck formwork in preparation for installing the concrete deck later in 2025.

Despite the winter conditions, Reed & Reed crews and the faithful spectators from Brunswick and Topsham are on hand daily!

By |2025-04-30T15:56:41+00:00February 5th, 2025|

Madawaska International Bridge

Madawaska International Bridge

The International Bridge project between Madawaska, ME and Edmundston, NB has progressed exceedingly well this year. Reed & Reed, and our subcontractors have all come together to complete the demolition phase of the project safely and on-schedule.

After the four steel trusses spanning the St. John River were removed, the pier demolition team worked overtime including nights and weekends to finish the removal of the existing bridge two weeks ahead of schedule.

With Phase 2 of the Canadian abutment construction now underway, there has been significant progress toward completing the last small piece of the new bridge structure. Despite encountering several challenges during the excavation of the previously built structure, the team has successfully installed the new abutment micro piles, placed the remaining abutment breast wall and bearing pedestal, and is now progressing with the construction of the wing wall and final steel erection.

The new $89 million bridge is 1800 feet long and soars nearly 100 feet over the St John River separating the United States and Canada and now reconnects commerce between the two communities.  The existing bridge had been posted to 5-ton limits.

By |2025-04-30T15:56:41+00:00February 5th, 2025|

Hinsdale, NH – Brattleboro, VT Bridge over Connecticut River

Hinsdale, NH – Brattleboro, VT Bridge over Connecticut River:

The Hinsdale-Brattleboro project is nearing completion.  All major work for Reed & Reed is done at this point and we opened the bridge on December 4, 2024.  The project had some major challenges, including an 18-month delay on Pier 1 and a flood during the Pier 2 seal placement to name a couple; but the crew’s determination and hard work prevailed, bringing the project in on time. Crews will be wrapping up final fencing, lighting and local road relocations as weather permits.

As NHDOT Commissioner Bill Cass said about the completion of this $64 million project, “A particularly proud moment came in early December 2024 with the ribbon-cutting ceremony the much-anticipated opening of the new General John Stark Memorial Bridge connecting Hinsdale, NH and Brattleboro, VT.”

Indeed, all of us at Reed & Reed are very proud of our work on this project.

By |2025-04-30T15:56:41+00:00February 5th, 2025|

Maine Maritime Academy Waterfront Facilities Upgrade

Maine Maritime Academy Waterfront Facilities Upgrade

Reed & Reed crews have begun building the new marine facility for Maine Maritime Academy’s new training vessel.  This $85 million project includes replacing the existing pier with a new, larger one, three new mooring dolphins, a breakwater and other ancillary upgrades.

The pile template is in place and production piling installation is underway.  Over 300 steel pipe piles will be driven to refusal and socketed into bedrock to support the new structures.  Precast pile caps and slabs will support the new concrete deck system.

By |2025-04-30T15:56:41+00:00February 5th, 2025|

Old Town Bridge Project

Old Town Bridge Project -

This project is a CMGC (Construction Manager General Contractor) model in which Reed & Reed is working under a CMGC agreement with the Maine DOT, alongside their Engineer, and other key stakeholders to finalize the design, as well as schedule and budget the project to meet the DOT’s needs.  This allows work to begin on the project as they are completing the design by issuing “Early Release Packages” (ERPs).

Early Release Package #5 is underway with onsite drilling of the pier sockets. Once the first three piles are socketed, we’ll begin building pile caps, which will sit on 54” FRP composite pile filled with a steel reinforcing cage and concrete.

ERPs #1-#4 provided for installation of the a 525 foot long temporary detour bridge, demolition of the two existing bridge superstructures, procurement of advanced technology composite bridge girders and other long-lead materials.

Once the bridge piers and abutments are complete we will take delivery of the superstructure beams and complete the deck. The superstructure beams are innovative composite girders being made in Winterport Maine.  Fabrication has begun and we expect to take delivery of the girders for the first bridge during summer 2025.

By |2025-04-30T15:56:41+00:00February 5th, 2025|

Augusta Western Avenue Bridge Replacement

Augusta Western Avenue Bridge Replacement Project

Augusta crews have been busy to end the year.  Our concrete crew has been working hard under the existing bridge for 9 months, placing over 1,000 yards of concrete on bedrock. They completed the final placement as a precursor to demolition of  the existing bridge.

Meanwhile, the crew built our 4-span, 50ft. wide detour bridge over I-95. They started with building the two 52’ spans on either end of the bridge followed by the middle spans over I-95 at night with the concrete crew prepping materials during the day. Everyone worked hard to get the detour finished and paved before the holidays.

We of course need to recognize and give a huge shoutout to our fabrication crews who built all the components in Woolwich. The crews built sixty-six, 50 ft. concrete slabs for our deck at our precast concrete fabrication facility on the banks of the Kennebec River  Also, thanks to the fab shop for fabricating all of our steel, rebuilding used steel, preparing pipe supports, and all the details to put together this 240’ detour bridge.

Meanwhile a crew at our Dockyard precast facility has been building our Precast Bridge Units this winter. They have received the structural steel beams and assembled the first sections of PBUs for casting. We will have a busy winter precasting our bridge before shipping it up to Augusta for assembly over busy I-95 next summer.

By |2025-04-30T15:56:41+00:00February 5th, 2025|