The Lisbon Center Bridge Street bridge work began in late June 2018 and was set on a fast track 4-month construction schedule to be completed and opened to traffic in the Fall of 2018. The project included the removal of a 2-span concrete T-beam bridge being replaced with a new 88-foot bridge span, composed of precast New England Bulb-Tee Girders with a 9” concrete deck and integral wearing surface. A sheet pile cofferdam on ledge was installed for the Abutment 1 foundation and a large sandbag cofferdam was utilized for the construction of Abutment 2 foundation. Also included in the project was approximately 450 feet of full depth approach work that Reed and Reed self-performed which included the installation of a new waterline and natural gas line.