Project Description

Reed & Reed was selected by L-P to construct the foundations and other related work for its Oriented Strand Lumber mill expansion. The overall project represents an investment of over $100 million and Reed & Reed’s work was on the project critical path for much of the duration. Work proceeded through the winter of 2006-07 to accomodate the follow-on contractors in this extremely complex project. In all, Reed & Reed formed and placed some 15,000 cy of reinforced concrete and hundreds of tons of critical embedments.

Location: New Limerick, Maine
Owner: Louisiana Pacific Corporation
Completed: December, 2007
Cost: $12 million
Contractor: Reed & Reed, Inc.