Project Description
Reed & Reed was chosen as the EPC contractor to work with Walden Green Energy on permitting and design for the 9 turbine project. Reed & Reed’s contract included Engineering & Design, Civil Infrastructure, WTG Foundations & Erection, Underground & Overhead Electrical Collector System, Collector Substation construction, MET Tower work and the Operations & Maintenance Building.
Reed & Reed’s scope included the construction of:
- Sitework and access roads/crane paths
- Wind Turbine Foundations
- 5 kV Collection System
- Collector Substation
- Transmission Line
- Wind Turbine Erection
Location: Antrim, NH
Owner: Walden/Transalta
Completed: 2019
Contractor: REED & REED